Open Context

Trench Layout

Trench Layout:

CB 41 was laid out on the master grid system established for the site (see TT-I, 1991, pg 173). A base line was shot with the transit which was situated at (94S, 1W). On this baseline, the two points (94S, 9 W) and ((94S, 13W) were established. Via triangulation the two other corners (90S, 9W and 90S, 13W) of the trench were established.

The coordinates of the four corners of CB 41 upon commencing excavation were as follows:

NW corner: 90S/13W

NE corner: 90S/ 9W

SE corner: 94S/ 9W

SW corner: 94S/ 13W

A datum point with an absolute elevation of 30.26m was established on a tree located immediately to the north-west of trench.

Plan of CB 41 upon commencing excavation

Property or Relation Value(s)
Temporal Coverage
[Standard: Dublin Core Terms]
Editorial Note

Open Context editors work with data contributors to annotate datasets to shared vocabularies, ontologies, and other standards using 'Linked Open Data' (LOD) methods.

The annotations presented above approximate some of the meaning in this contributed data record to concepts defined in shared standards. These annotations are provided to help make datasets easier to understand and use with other datasets.

Suggested Citation

Eóin M. O'Donoghue. "EMO II (2010-07-27):15-19; Trench Layout from Italy/Poggio Civitate/Civitate B/Civitate B 41/2010, ID:631". (2017) In Murlo. Anthony Tuck (Ed.) . Released: 2017-10-04. Open Context. <http://opencontext.org/documents/0b0f28f9-58dd-475e-a68a-db3b3c9cf4cd>

Editorial Status

●●●○○
Managing editor reviewed

Part of Project

Murlo

Mapping Data

Copyright License

Attribution 4.0

To the extent to which copyright applies, this content carries the above license. Follow the link to understand specific permissions and requirements.
Required Attribution: Citation and reference of URIs (hyperlinks)